History

Sakhalin Energy was founded in 1994 to develop the Piltun-Astokhskoye and Lunskoye oil and gas fields off the north-eastern coast of Sakhalin Island. Key Sakhalin-2 project milestones are listed below:

1994
April

June

 


Sakhalin Energy Investment Company Ltd. (Sakhalin Energy) is established to implement the Sakhalin-2 project (development of the Piltun-Astokhskoye and Lunskoye fields)
The Sakhalin-2 PSA on the development of Piltun-Astokhskoye and Lunskoye fields is signed by the RF Government, the Sakhalin Oblast Administration, and Sakhalin Energy

1996
May-June
June


The Russian Federation issues licences to Sakhalin Energy for the Piltun-Astokhskoye and Lunskoye fields
The Company starts the development of the Astokh Area of the Piltun-Astokhskoye field

1998
September


Molikpaq, the first Russia`s stationary platform, installed at the Piltun-Astokhskoye field by Sakhalin Energy

1999
July


First oil production at the Piltun-Astokhskoye field, Molikpaq platform

2003
May


The Company starts the integrated development of the Piltun-Astokhskoye and Lunskoye fields

2006
June


Sakhalin Energy completes construction and installation works for the Lunskoye-A (LUN-A) offshore gas production platform

2007
July


The Piltun-Astokhskoye-B (PA-B) platform, the third offshore ice-class production platform, is completed and installed

2008
June
October
December


A project funding agreement totalling US$ 5.3 bln is signed
Construction work on the TransSakhalin pipeline system is completed successfully
Sakhalin Energy begins year-round oil exports via its Oil Export Terminal (OET) at Prigorodnoye Asset

2009
January
February

October


Russia`s first offshore gas production begins at the Lunskoye-A (LUN-A) ice-resistant platform
Russia’s first LNG plant inauguration ceremony
A project funding agreement totalling US$ 1.4 bln is signed

2010
July


The first-ever 4D seismic in Russia is completed successfully

2012
March
August

 


Production sharing begins
The 500th cargo of Sakhalin LNG is successfully offloaded from the Prigorodnoye Asset

 

First oil from Molikpaq (PA-A), July 1999

 

Onshore pipeline construction, 2005

 

Lunskoy-A (LUN-A) platform after installation, 2007

 

LNG plant, 2009